This is example of resource creation and assignment. We already have a project file and two tasks:
First we will add resources to the project:
[C#]
Resource resource1 = file.AddResource();
resource1.Name = "Resource1";
Resource resource2 = file.AddResource();
resource2.Name = "Resource2";
[Visual Basic]
Dim resource1 As Resource = file.AddResource()
resource1.Name = "Resource1"
Dim resource2 As Resource = file.AddResource()
resource2.Name = "Resource2"
And then we'll assign them to the tasks:
[C#]
ResourceAssignment assignment1 = task1.AddResourceAssignment(resource1);
ResourceAssignment assignment2 = task2.AddResourceAssignment(resource2);
[Visual Basic]
Dim assignment1 As ResourceAssignment = task1.AddResourceAssignment(resource1)
Dim assignment2 As ResourceAssignment = task2.AddResourceAssignment(resource2)