Hi,
We are going to add some additional tests for TotalSlack calculation to our testing engine. Now all added tests are passed correctly. May be the project data is not recalculated in the files or damaged? We have to wait the additinal tests' results.
I have added a new issue 'Read StartVariance and FinishVariance for tasks and resource assignments from MS Project 2003/2007/2010 MPP files.' with ID = 18893 and linked to this forum thread. We are going to resolve the issue in August's release (end of this August).
You can read information about properties' reading formats currently supported from Aspose.Tasks for .NET Documentation chm file in your Aspose.Tasks installation folder Help subfolder. See a screen shot attached. But the information is not provided on our web site. So I have created a new issue 'Update Aspose.Tasks .NET Web documentation in part of data reading support for different file formats.' with ID = 18894 and linked it to this forum thread too.
Unfortunately we can not provide you with the information when all project's fields and properties reading support will be added just now, but we are working hard in this direction. For example, in our last release the support for 21 project's common properties was added. You can provide us with a list of all values you need and we'll put them in our high priority list.
Sorry for inconvenience and thank you for your cooperation.
Sergey PolshkovTeam Leader, Aspose.Tasks & Aspose.Diagram Team
http://www.aspose.comYour File Format Experts
Keep in touch! We're on
Twitter and
Facebook